Design and Construction Supervision of Solar Water Heating System

Project NameDesign and Construction Supervision of Solar Water Heating System

ConsultantConsultants of Technology Co., Ltd. (COT)

Site 1 : Panya Golf Club Ram-Indra

Location Bangkok, Thailand

Owner Panya Property Co., Ltd.

Description Panya Golf Club implements solar water heating system to consolidate  with 3 sets of conventional LPG Burner, to produce 15,000 litres of hot water daily at 60oC for dish washing and shower for golfers. The club obtains reduction on LPG consumption and lower maintenance costs of burners as extra saving.

Construction Cost 3.2 Million Baht (0.08 Million $US)(1 $US : 40 Baht)

COT Engagement

1. Design of Solar Water Heating System

2. Construction Supervision

Duration October – December 2003

18

Site 2 : D2 Hotel

Location Chiang Mai Province, Thailand

Owner Dusit Thani Public Co., Ltd.

Consultant Consultants of Technology Co., Ltd. (COT)

Description D2 Hotel is located just off the famous Chang Klan Road, in the heart of downtown Chiang Mai, with 130 guest rooms and 12 floor building. The expected hot water amounted 15,000 litres/day and temperature required is 60oC.

Construction Cost 2.6 Million Baht (0.065 Million $US) (1 $US : 40 Baht)

COT Engagement

1. Design of Solar Water Heating System

2. Construction Supervision

Duration December 2004 – April 2005

19

Site 3 : Dusit Thani Hotel

Location Bangkok, Thailand

Owner Dusit Thani Public Co., Ltd.

Consultant Consultants of Technology Co., Ltd. (COT)

Description The Hotel’s Energy Conservation program is to use solar water heating system for their “E-wing” which comprises of 14 floors and 265 guest rooms. Hot water requires 13,000 litres/day and temperature required is 55oC for guest rooms.

Construction Cost 2.3 Million Baht (0.056 Million $US) (1 $US : 41 Baht)

COT Engagement 

1. Design of solar water heating system

2. Construction supervision

Duration September - December 2005

20

Site 4 : President Rice Product (PLC) Co., Ltd.

Location Ratchaburi Province, Thailand

Owner President Rice Product (PLC) Co., Ltd.

Consultant Consultants of Technology Co., Ltd. (COT)

Description The factory requirement  is to heating up raw water 12,000 litres/day up to temperature 60oC before feeding into boiler for energy conservation by reducing  heavy oil fuel.

Construction Cost 1.5 Million Baht (0.036 Million $US)(1 $US : 41 Baht)

COT Engagement 

1. Design of Solar Water Heating System

2. Construction Supervision

Duration October 2005 – January 2006

21